Korea Hydro & Nuclear Power (KHNP) said it had ended negotiations with Daewoo E&C over the selection of a contractor for the Czech Republic’s Dukovany nuclear power plant, and that it had not selected a particular construction company in advance as the new contractor. KHNP said the parties had held discussions for 15 months but failed to agree on key contract terms, and rejected allegations by the Daewoo E&C union that it had deliberately broken off negotiations to hand the construction contract to a particular company.[1]

The 91 rounds cited by KHNP comprise two CEO meetings, 78 working-level meetings, and 11 meetings of the dispute mediation committee. Regarding the schedule, KHNP said the Czech project owner had asked it to finalize the construction contract by September, but that KHNP had conveyed its position that negotiations would conclude by the end of October to secure more time for discussions, and had shared this with Daewoo E&C in advance.[1]

The contract structure was also a point of contention. KHNP claimed that Daewoo E&C had agreed to a fixed-price contract during the 2022 and 2023 bidding rounds, but changed its position in the final bid in April 2024. KHNP said that on the 7th of last month, it proposed increasing the contract amount within the existing negotiation framework to reflect the expected increase in quantities, then finalizing the price to reflect revised quantities when the basic design is approved in July 2029. It said it agreed to actual-cost settlement for underground civil engineering work, where quantities are difficult to forecast, and additionally calculated construction costs arising from adjustments to the scope of work after submission of the final bid, reflecting them in the negotiations. It also said it proposed allowing subsequent changes to the scope of work to be handled through contract amendments. KHNP acknowledged that Daewoo E&C’s revised proposal, submitted on the 29th of last month, included an adjustment to the amount, but said the parties could not reach agreement because differences remained over major contract terms, including settlement conditions for detailed design quantities.[1]