The Ministry of Climate, Energy and Environment said it agreed on a draft consultation agreement for expanding the Dong Seoul Converter Station with representatives of residents in the Gam-il District at the National Assembly on November 25, 2026. The draft will be finalized through a resident vote among all household heads in the district’s 19 apartment complexes. If approved, it will be signed by the resident representatives, the Ministry of Climate, Energy and Environment, KEPCO, and the office of National Assembly member Lee Kwang-jae, and will take effect on the day it is signed. The agreement was drawn up after 17 meetings since the consultation committee was launched on August 26, 2026.[2]

A third-party specialist agency will verify KEPCO’s submitted review materials on relocating to an alternative site, as well as materials on resident safety and environmental impacts, including electromagnetic waves, noise, and fire. If the final verification finds a serious defect or hazard, KEPCO will suspend administrative procedures, and the Ministry of Climate, Energy and Environment will request necessary follow-up measures and check whether they are carried out. The draft agreement also provides for applying electromagnetic shielding materials to the converter station building and for checking electromagnetic waves and noise with residents after completion.[2]

Issues Raised in Reports Before the Agreement

Before the agreement, on November 23, the Electric Times reported a plan to proceed with the existing expansion procedures while verifying the feasibility of relocating to a third site. The report said verification could take several months or longer and identified the selection of the verification agency, the scope of verification, and specific follow-up measures based on the results as outstanding tasks. These were the planned approach and issues described in reports before the agreement.[1]

A report on the same day, November 23, described the voters as residents of the 19 apartment complexes in Gam-il-dong and said resident representatives planned to decide whether to accept the consultation document based on the results. At the time, the requirements for a valid resident vote, the approval threshold, and the response in case of rejection were also cited as future variables. In a subsequent announcement, the Ministry of Climate, Energy and Environment said that all household heads in the 19 complexes were eligible to vote and that the draft agreement would be finalized by resident vote.[2][1]