The International Energy Agency (IEA) forecast that offshore wind farms with a total capacity of 1.7 GW would be completed in South Korea in 2026–2030. This is lower than the 2.8 GW that the previous year’s report projected would newly enter the grid over the same five-year period. The IEA cited grid connection difficulties and delays in administrative procedures as reasons for the downward revision.[1]

According to a Seoul Economic Daily report, the forecast also reflects delays in infrastructure such as transmission networks and in permitting procedures, as well as the increased burden on developers from rising prices for major equipment and components. The government is pursuing dedicated offshore wind ports and installation vessels, but the IEA analyzed that these infrastructure efforts would begin to have an effect after 2031.[1]

Examples of Project Delays

The Jeonbuk Southwest Offshore Wind Farm set a target of expanding from a 400 MW pilot complex to as much as 2.4 GW, but prolonged consultations with military authorities on operational compatibility increased uncertainty around the project, and Korea Western Power decided to withdraw from the consortium. The Anma Offshore Wind project also stalled even after being selected in a long-term fixed-price contract tender and signing an REC trading agreement. After the military operational review was resolved to some extent, foreign controlling shareholders attempted to sell their stakes, citing worsening project viability, and the project came to a halt. Domestic companies that had signed supply contracts for substructures and subsea cables also decided to suspend or terminate their contracts.[1]