On November 20, 2026, the Ministry of Science and ICT announced proposed enforcement decree and enforcement rules for the Special Act on the Promotion of the Artificial Intelligence Data Center Industry. The proposal defines which facilities qualify as AI data centers and sets out exemptions from assessments outside the capital region, priority processing for large-scale projects, and permitting procedures.[2]

The criteria are met if power supplied to racks equipped with GPUs or NPUs is at least 250 kW and accounts for at least 50% of the total power for IT equipment, or if the power capacity of the relevant rack is at least 5 MW. The definition also includes colocation facilities that provide operators with space equipped with power and cooling systems, even if they do not operate AI racks directly.[2]

Exemptions and Priority Processing Are Different

AI data centers built, expanded, or converted to a different use outside the capital region are exempt from the power system impact assessment if their contracted power is 50 MW or less. The Ministry of Science and ICT said it set the 50 MW threshold alongside a separate priority processing measure, taking into account that raising the exemption threshold to 100 MW would still leave most gigawatt-scale projects outside its scope and that project operators spend considerable time preparing for non-technical assessments.[3][2]

Facilities that are megaprojects or have applied for integrated permitting under the Special Act are planned to receive priority processing for the power system impact assessment, regardless of size. In particular, gigawatt-scale megaprojects will be eligible for the fast track. Priority processing advances the assessment in the queue rather than eliminating it, and is distinct from exemptions from non-technical assessments in special zones.[1][3][2]

Non-technical assessments will be waived in AI data center special zones, but EDaily reported that technical assessments examining the impact on the power system will remain in place. It also reported that the power demand score bands in technical assessments may be adjusted when non-technical assessments are waived. A local government seeking special-zone designation must submit plans covering the project, infrastructure, financing, power system, and acceptance of resident and regional coexistence measures. The Ministry of Science and ICT will review the application within 90 days, and designation will follow a resolution by the AI Committee.[1][2]

Power Supply and Phased Expansion

Industry concerns that facility operations could be delayed if the region lacks sufficient power supply capacity, even after an assessment is completed early, were reported by ZDNet. It also reported views that expanding transmission networks and substations requires separate procedures and construction time. Therefore, the speed of assessment processing and the actual timing of power supply should be considered separately.[4]

At a public discussion in September 2026, participants raised the need to improve the system for modular data centers that add equipment in stages according to demand. ZDNet reported that the proposed legislation includes notification procedures for changes in facility scale and power, but does not explicitly provide special provisions for modular facilities.[4]

The proposal requires relevant agencies to respond to permitting requests within 10 days; if they do not respond by the deadline, the application will be processed in full based on the submitted documents. The Ministry of Science and ICT plans to seek public comment during a 40-day legislative notice period ending December 30, 2026. The Special Act and its subordinate legislation are scheduled to take effect on March 10, 2027.[2]